ConocoPhillips starts production at Coyote 3SX on Alaska’s North Slope
Steady2 outlets reported this in 2 reports over 2 days
Thu, 13 August 2026Wed, 19 August 2026
What it is about
ConocophillipsBp Energy Company Of KirkukValdez Marine Terminal, Alaska, United StatesKuparuk River, Alaska, United StatesAmericaKirkuk, At Ta'mim, IraqIraqNorth Slope, Alaska, United StatesPrudhoe Bay, Alaska, United StatesAlaska, United States
Who published it, and when
original reportfirst to report
yahoo.com
worldoil.com
13 Aug, 08:30over 6 days19 Aug, 20:00
How it spread - 2 original reports
Thu, 13 August 2026
1 report- yahoo.com08:30first to report
The company approved funding of approximately $800m for the project in October 2025.
Wed, 19 August 2026
1 report- worldoil.com20:00
ConocoPhillips has achieved first oil ahead of schedule and under budget from its $800 million Coyote 3SX development in Alaska’s Kuparuk River Unit, with peak production expected to reach 12,000 bpd.